Key Facts:
- $1.7 billion total project cost
- $1.3 billion government grant
- 350 beds, with capacity to expand to 550
- 1.2 million square feet
Cortellucci Vaughan Hospital brings:
- Over 1,000 construction jobs (based on stats for comparable-sized hospital projects)
- Approximately 1,500 new staff positions
- Approximately 100 new physicians
- Approximately 350 volunteers
Key Milestones
- Hospital opens as a full-service hospital for the community: June 2021
- Hospital opens as a system solution to fight COVID-19: February 2021
- Construction completion: August 2020
- Name announcement: June 2020
- Topping-off: October 2018
- Groundbreaking: October 2016
- Commercial and financial close: October 2016
- Request for Proposals release: June 2015
- Request for Qualifications release: March 2014